Case Studies
C Butt Ltd
- Location – Magna Park, Lutterworth
- Project Description – Warehouse Lighting
- Contract Value – Circa £170,000 (Net)
Scope of work:
- Supply and fit warehouse lighting to include a new overhead Busbar system, three-phase distribution boards, Low Bay light fittings and Twin Spot Emergency Lighting
- Install power supplies within the warehouse for heaters, security cameras & alarms, battery charging area and general use sockets
Special Features
- Worked with manufacturer to produce lighting scheme for the client and their landlord’s approval that would fit within the client’s available budget
- Agreed a tight project timeline with the client to fit with other services being installed during the programme and achieved the milestones set out
Barsan Global Logistics
- Location – Prologis Park, Coventry
- Project Description – Warehouse Lighting
- Contract Value – Circa £71,000 (Net)
Scope of work:
- Supply and fit warehouse lighting to include three-phase distribution, fluorescent light fittings and Twin Spot Emergency lighting
Special Features
- Occupancy controlled lighting with natural daylight override facility
Ricardo MTC
- Location – Midland Technical Centre – Leamington Spa
- Project Description – Building’s One & Two
- Contract Value – Circa £175,000 (Net)
Scope of work:
- Building One was a single storey office refurbishment for one hundred desks involving a new suspended ceiling, a Cat2 lighting scheme, new three-phase distribution boards, Cat5e structured cabling and small power circuits
- Building Two was a two-storey refurbishment involving structured cabling, 300 floor boxes supplying three Cat5e network connections and 13amp power, new three phase distribution boards and a new communications room complete with 19` cabinet suit
- Installation of new campus wide fibre optic connectivity
- Installation of multicore cross-site voice cabling
- Main reception area refurbishment including structured cabling, small power and an aesthetic lighting scheme
- Workshop/Shop Floor refurbishment including lighting, three phase power and machine moves
Special Features
- Benefit from occupancy control lighting system identified by J&B and approved by the client
- Campus/Car Park street lighting installed incorporating civil works and reinstatement of the landscape
- Provision of ceiling grids and carpets incorporated into J&B remit to provide a turnkey solution
Dunlop Aerospace (Fluid Dynamics)
- Location – Coventry
- Project Description – Repair/replace fire damaged electrical services
- Contract Value – Circa £38,000 (Net)
Scope of work:
- Attend site immediately and assess damage caused by a fire
- Effect immediate repairs to enable some areas of the plant to return to production
- Strip out and replace damaged electrical installation
Special Features
- J&B were able to attend site the day after the fire and start work immediately to get the plant running again in the shortest possible time
Midland Steel Structures Ltd
- Location – Coventry
- Project Description – New Building
- Contract Value – Circa £39,000 (Net)
Scope of work:
Workshop:
- Supply and fit new three phase panel board
- Supply and fit new three phase sub distribution boards
- Supply and fit low bay light fittings and emergency lighting
- Supply and fit 415V, 240V & 11OV supplies for various machines and general use
- Supply and fit fans in the roof
Office Area:
- Supply and fit office and general lighting
- Supply and fit small power requirements
General:
- Supply and fit external lighting
- Supply and fit fire alarm system
Special Features
- External lighting fitted with daylight sensors and timer facility
Steel Construction Ltd
- Location – Coventry
- Project Description – Electrical refit to Shop Floor
- Contract Value – Circa £41,000 (Net)
Scope of work:
- Supply and fit new three phase panel board
- Supply and fit new three phase sub distribution boards
- Supply and fit low bay light fittings and emergency lighting
- Supply and fit 415V, 240V & 11OV supplies for various machines and general use
Special Features
- Incorporated several variations and new instructions from the client into the original project timescales
Optilan UK Ltd
- Location – Coventry
- Project Description – Electrical & Network Cabling installation to new offices
- Contract Value – Circa £87,000 (Net)
Scope of work:
- Supply and fit new three phase panel board
- Supply and fit new three phase sub distribution boards
- Supply and fit Cat2 office lighting
- Supply and fit high level warehouse lighting
- Supply and fit small power requirements
- Installation of Cat6 structured cabling system
Special Features
- Worked with other trades on site to achieve programmed milestones and the clients moving in date
Nomenca
- Location – Birmingham International Station
- Project Description – Lighting & Distribution Upgrade
- Contract Value – Circa £81,000 (Net)
Scope of work:
- Replace lighting on platforms and concourse level
- Replace distribution boards throughout
- Replace sub-main cables throughout
Special Features
- Kept lighting on to all areas throughout the project
- Worked unsociable hours to meet project schedules
Briggs & Forrester MEP Ltd
- Location – University of Birmingham – Masons Hall
- Project Description – Electrical installation to new student accommodation blocks
- Contract Value – Circa £237,000 (Net)
Scope of work:
- Full electrical installation to over one hundred, six bed and kitchen apartments
- Sub main cabling to each flat
- Landlords cabling to common areas and stairwells
- Street Lighting to campus
Special Features
- Flexible approach to changing deadlines and project milestones over twelve months